Summary
of January 21, 2005
Corridor Consensus Committee (CCC) Meeting
Return to the main page of Public Involvement
Corridor Consensus Committee
Jan. 21, 2005
12 – 4 p.m.
Action Items:
The study team will look into adding ramps at US 6 for modeling purposes.
At the Table:
| Suzanne Ghais |
Steve Holt |
Peggy Catlin |
| Edie Bryan |
Preston Gibson |
Gretchen Cerveny |
| John Muscatell |
Pam Hutton |
Ron Speral |
| Karl Buchholz |
Alex Ariniello |
Joe Jehn |
| Lorraine Anderson |
Kevin Standbridge |
Jim Congrove |
| Chuck Baroch |
Don Dunshee |
Dave Downing |
| Andy Schultheiss |
Steve Dole |
Will Singleton |
| Karen Stuart |
Edie Bryan |
Carol Kesselman |
In the Gallery:
| John Putnam |
Steve Dole |
Dick Sugg |
| Yates Opperman |
Caelan McGee |
Dick Ward |
| Bob Manwaring |
Steve Rudy |
Elliot Sulsky |
| Rob Refvem |
Bill McDonnell |
Moe Awaznezhad |
| Steve Sherman |
Bruce Naylor |
Nanette Neelan |
| Deb Lebow |
Michael Zinna |
|
Introductions
There are a number of new CCC members who have joined the group since
the last meeting. They are:
Jim Congrove — Jefferson County Commissioner, replaces Michelle
Lawrence
Edie Bryan — Replaces Bert Melcher as Environment Representative
Pam
Hutton — CDOT Region 6 Director replaces John Muscatell
Project Status
Merger Agreement with US Army Corps of Engineers
- The merger agreement has been finalized—it will be on the CDOT
external Web site as soon as possible.
- It says how the principals of the study can work together to ensure
that given different NEPA guidelines among the lead agencies that the
FHWA NEPA process results in the Least Environmentally Damaging Preferred
Alternative (LEDPA), as required by the Corps of Engineers NEPA process.
- If you screen on natural or social environment, the process should
demonstrate that impacts to the aquatic resources are considered for
best outcome.
- Alignments that abut the Great Western Reservoir may be a LEDPA question.
FHWA Memo on Tolling
- CDOT requested the memo in reference to C-470.
- CDOT observed that a Record of Decision (ROD) is not possible without
an expectation of funding.
- The memo outlines three times when tolling can be the selected alternative
by an EIS:
- If a tolling proposed action comes out of the planning process—this
has not yet been an issue.
- If Purpose and Need is written so
that only tolling can be the satisfactory alternative. Courts say
it is difficult to define so narrowly.
- If tolling is not part of
Purpose and Need, and all alternatives are considered and evaluated
but the only way to build an alternative is through a tolling option.
This is the only scenario that could potentially apply to our case,
but the memo includes many cautions with this possibility.
Schedule: Because DRCOG data was delayed, results of 3C will be delayed
to the end of March.
Results of 2030 Modeling and Level 3A Screening
The results of Levels 3Ai, 3Aii, and 3Aiii were reviewed for CCC members
based on the packet distributed to them and a PowerPoint presentation.
3Aii Evaluation and Screening Results
- 3Aii – eliminated five alternatives that don’t meet minimal
transportation performance measures. These include:
- RA (SH 128 to SH 93 west of Rocky Flats) does not draw as many
trips as other alternatives and is higher in environmental impacts
than most alignments.
- RD (RD along Wadsworth) does not address many trips on western
side of study area, has low connectivity and does not address Purpose
and Need well.
- NW Quadrant Feasibility Study alternative.
- As per previous discussions, modeled as suggested in final report
of NWQFS without modifications. Did not fit Purpose and Need well.
- Two stand alone Transit Alternatives.
- The Transit Alternatives show only 1,400 daily additional riders,
and are modeled as serving on the order of 1% of trip demand and
do not perform well as stand alone alternatives.
3Aiii Evaluation and Screening Results
- 3Aiii – eliminated an additional four alternatives. These were
screened on considerations such as transportation performance, significant
property takes and impacts to natural environments.
- FG and FH – these alternatives have the same alignment
as the FB and FC options, but were screened due to a narrower footprint
that does not provide an envelope for future transit expansion.
- FF – there are a large number of building takes (245).
- FI – there are a large number of building takes (244).
Remaining Alternatives
Six alternatives, in addition to the No Action alternative, remain after
the level 3Aii and 3Aiii screening. They include a freeway (FB), tollway
(TB) and regional arterial (RB) alternatives on the Indiana/SH 93/US
6 alignment and a freeway (FC), tollway (TC) and regional arterial (RC)
alternatives on the Indiana/McIntyre alignment.
- FB—alignment close to Great Western Reservoir will cross to
the west for LEDPA reasons.
- RB is a regional arterial that uses the Rocky Flats buffer. The functional
classification “regional arterial” means similar to Santa
Fe Drive with a combination of at-grade intersections and grade-separated
interchanges. 3C evaluation will look at the regional arterials in
detail to delineate where the interchanges and intersections go and
can be improved. 3A modeling and screening did not require determining
where intersections and interchanges will be.
Steve Holt Reviewed Tables T-1 through T-5 in the CCC Packets. These
tables demonstrated the use of modeling based on DRCOG 2030 data to screen
alternatives in 3A.
Key points were:
- The TSC agreed that Vehicle Hours Traveled (VHT) should be one of
the screening measures.
- The speed of the facility and its incumbent capacity is defined by
the functional classification.
- System Connectivity is a qualitative measure related to driver expectancy.
Freeways and tollways score higher because of the expectation of interregional
traffic to have unencumbered flow of traffic. The “C” alignments
got a poorer rating than the “B” alignments because they
would require taking exit ramps to get from point A to point B.
- 2030 RTP (with the exception of some transit build out beyond FasTracks)
demonstrates a version of “unconstrained” modeling to determine
if there is latent traffic demand that is not being met by No Action
or specific stand alone alternatives.
- TB and RB modeling was revised to more accurately show volume/capacity
ratios.
- Models may need to be further refined as the team finds inconsistencies.
- The remaining alternatives are just variations on two alignments.
The performance discernment is the difference among the alternatives
for the two alignments.
The study team will look into the need to add ramps at the I-70/US 6
interchange to the eastern alignment alternatives.
The CCC members were asked if they would like to have any specific screened
alternatives explained. No CCC members responded with a desire to have
specific explanations for screening.
Level 3B Merging and Packaging
The Technical Study Committee developed a series of sketch ideas using
the framework guidelines and using portions of previously evaluated alternatives
that were carried forward from 3Aiii.The sketches were graphically portrayed
on the wall. The CCC was asked to review the options, to add to them
if necessary and then to eliminate ones that did not seem necessary or
ones that were duplicative.
CCC members were asked to give their feedback on the sketches proposed.
As they were giving their feedback, they were asked to state what options
they preferred and why they preferred them. The CCC gave their preferred
options along with their key interests. As each CCC member was asked
to give input, they highlighted the following packages:
MP-10- [Combines TB from NW Parkway south to SH 93
where it becomes a major regional arterial with a regional arterial or
a principal arterial in the “C” alignment south of 86 th Parkway
on Indiana/McIntyre to SH 58. Interlocken may also be a regional arterial.]
- If you have to have a toll road, MP-10 makes sense because when it
hits SH 93 it is no longer a toll road.
- Tolling could go south to just outside the limits of Golden and still
satisfy Golden’s need for local access in a MRA.
P-2- [Combines RC (from NW Parkway, down SH 128, south on Indiana,
south on SH 72, south on McIntyre to SH 58) and NWQ-R (SH 72 west of
Indiana, SH 93, and US 6 to C-470].
- It gives locals access with little cost.
- Would serve the same purposes as analyzing the two regional arterial
packages.
MP-8- [Combines TB and RB with a regional arterial facility on Interlocken,
a toll road along the TB alignment from Simms Street to close to SH 93
and 64 th Avenue, and a regional arterial through Golden to US 6 and
US 40. Also includes a four lane primary arterial down Indiana/McIntyre
south of 86 th Parkway.]
- Modify M-8 to include 4 lanes down McIntyre.
Interests/Concerns:
CCC members were asked to state their key interests for the study and
relate the interests to the sketches presented. The following is a summary
of priority interests given by CCC members:
- Community cohesion (related to the elimination of Ward Road alternatives).
- Respecting the wishes/needs of Golden residents and minimizing impacts
on their quality of life.
- Protecting Westminster’s water supply.
- Being able to pay for additional capacity.
- Meeting of the needs of the metro area for an interregional facility.
- Getting regional traffic off of local streets.
- Access through Interlocken for local traffic.
- SH 128 and Simms would have to be engineered to provide access.
- This facility should not draw construction money from other important
projects ( US 36).
- Decrease VMT and VHT.
- Minimize environmental impacts including sprawl, air pollution, and
toxics.
- Include alternative forms of transportation in the study and the
ultimate preferred alternative.
- Job creation through better access to the remaining developable land
in Jefferson County.
- Connecting A-B.
- Reach a doable solution that has the support of major communities
in the study area.
- McCaslin Boulevard needs to stay a two lane facility.
- Address safety issues on SH 93.
On Tolling:
A toll facility is one of the clear ways to finance a new facility in
the study area. Budget constraints show few other obvious options. It
is possible that funds from tolling might be used for mitigation, making
the broader project more acceptable to affected communities. Toll funds
will not be used to build other facilities outside of the study area.
It is not expected that the toll road would have surplus revenue. The
state expects that it would have to contribute funds in order for the
tolling facility to be viable. Overall costs with a toll road would still
be considerably less.
Results of Discussion:
Two merged/packaged alternatives were identified by the CCC.
One was a blend of MP-10 and MP-8, because of its ability to address
interests represented by the two packages."MP-8a
blended" would
include a regional arterial at Interlocken/Flatirons to provide access.
It would also include a regional arterial through the Golden city limits
at the southern end, and a tollway in between along the “B” alignment.
It would also include a principal arterial (meaning with at-grade intersections
only, no grade-separated interchanges) down Indiana and McIntyre.
The other preferred package was P-2.
The CCC recommended that these two merged/packaged proposals be included
as alternatives which best address the collective community interest.
Therefore, it was jointly agreed that eight alternatives (these two
packages plus the six stand-alones) could be modeled and further evaluated
in Level 3C evaluation. Some discussed the ability of P-2 to effectively
represent the benefits of the regional arterial alternatives (RB and
RC). The Project Management Team will consider this possibility.
Public Comment
Michael Zinna —Only ten minutes allotted for public comments.
That is insulting. If I’m not mistaken you have spent $8 million.
That is a joke but I am not laughing. Four years ago I planned a project
at the Jefferson County Airport. I sat down with my partner and drew
on a napkin where the highway would go. The further this study progresses,
the closer it gets to what I drew on the napkin. This is a gigantic waste
of money.
Dick Sugg—We all know that building around the Jefferson County
Airport is going to create jobs. The presumption that all of these new
jobs are going to Jefferson County residents is flawed. People live in
Jefferson County because it is a great place to live.
Return to the main page of Public Involvement
Agency Scoping Meetings
Summary
of the January 21 agency scoping meeting.
Public Meetings
Public Meeting Summaries
Corridor Consensus Committee (CCC) Meetings
CCC Meeting Agendas
and Summaries
Technical Study Committee (TSC) Meetings
TSC Meeting Agendas
and Summaries
Citizen Working Group (CWG) Meetings
CWG Meeting Summaries
|